陈苏社. 特殊地质条件下综采工作面顶板控制技术[J]. 煤炭科学技术, 2014, (2).
引用本文: 陈苏社. 特殊地质条件下综采工作面顶板控制技术[J]. 煤炭科学技术, 2014, (2).
CHEN Su-she. Roof Control Technology of Fully- Mechanized Coal Mining Face Under Special Geological Conditions[J]. COAL SCIENCE AND TECHNOLOGY, 2014, (2).
Citation: CHEN Su-she. Roof Control Technology of Fully- Mechanized Coal Mining Face Under Special Geological Conditions[J]. COAL SCIENCE AND TECHNOLOGY, 2014, (2).

特殊地质条件下综采工作面顶板控制技术

Roof Control Technology of Fully- Mechanized Coal Mining Face Under Special Geological Conditions

  • 摘要: 为解决特殊地质条件下综采工作面顶板大面积垮落、过空巷及薄基岩巷道支护困难、末采期间冒顶事故多发、回采期间空顶距离长等顶板控制难题,以大柳塔煤矿和活鸡兔煤矿为研究对象,在综采工作面采取初采期间超深孔爆破强制放顶技术、准确判断顶板初次来压技术、过空巷顶板控制技术、过薄基岩顶板控制技术、末采顶板控制技术、回采期间架后悬顶处理技术等措施,有效控制了顶板事故的发生。

     

    Abstract: In order to solve frequently roof accidents occurred of the fully- mechanized coal mining face under the special geological condition, for example, the lar ge area roof falling occurred during the fully- mechanized coal mining period, difficult support when the coal mining face passing through the abandoned gateway and th e thin base rock gateway, many roof falling accidents occurred at the terminal mining period and the long distance of no support roof during the coal mining period, taki ng Daliuta Mine and Huotuji Mine as study objects, a blasting forced roof falling technology with ultra deep boreholes at the initial mining period, accurately judge initial roof strata weighting technology, roof control technology of the coal mining face passing through abandoned gateway, roof control technology of the coal mining face pa ssing through thin base rock, roof control technology of the terminal coal mining face, beyond powered support suspended roof control technology during the mining per iod and other technologies were applied to control the roof accidents. The site application results showed that roof accidents were effectively controlled by above meas ures taken.

     

/