Advance Search

LI Wenjing,QIU Li,LIN Zhiyong,et al. Periodic preventive maintenance strategy of open-pit mine truck based on age-reduction model[J]. Coal Science and Technology,2023,51(4):209−214

. DOI: 10.13199/j.cnki.cst.2021-1236
Citation:

LI Wenjing,QIU Li,LIN Zhiyong,et al. Periodic preventive maintenance strategy of open-pit mine truck based on age-reduction model[J]. Coal Science and Technology,2023,51(4):209−214

. DOI: 10.13199/j.cnki.cst.2021-1236

Periodic preventive maintenance strategy of open-pit mine truck based on age-reduction model

Funds: 

National Natural Science Foundation of China (51804224)

More Information
  • Received Date: May 08, 2022
  • Available Online: May 14, 2023
  • In view of high maintenance cost of trucks in the production and transportation of open-pit mine, a combination of periodic preventive maintenance and minor repairs was adopted for truck. Considering the change rule of failure rate after periodic preventive maintenance of open-pit mine truck, based on age-reduction model, periodical preventive maintenance strategy of open-pit mine truck was studied. According to the characteristics of the weibull distribution of open-pit mine truck failure rate function, introducing age-reduction factor to reflect change in the failure rate of open-pit mine truck after each cycle of periodic preventive maintenance, established the failure rate function of open-pit mine truck after each cycle of periodic preventive maintenance. Based on the failure rate function of open-pit mine truck, total preventive maintenance cost model including periodic preventive maintenance costs and minor repair costs of open-pit mine truck was established, and solution algorithm was designed to obtain optimal periodic preventive maintenance strategy for open-pit mine truck. The results show that: when operating time of open-pit mine truck was determined, preventive maintenance cost first decreases and then increases with the increase in the number of preventive maintenance, and first becomes smaller and then larger as the preventive maintenance cycle becomes longer; As the operating time increases , the number of optimal preventive maintenance increase slower; The optimized periodic preventive maintenance strategy for open-pit trucks requires less cost than the common maintenance strategy, and the difference becomes larger as the operating time becomes  longer. Constructing failure rate function of open-pit mine truck based on the age-reduction model, and to study the periodic preventive maintenance strategies of trucks with different operating hours, which can provide effective solutions for preventive maintenance and management of mining equipment.

  • [1]
    MORAD A M,POURGOL-MOHAMMAD M,SATTARVAND J. Application of reliability-centered maintenance for productivity improvement of open pit mining equipment: case study of sungun copper mine[J]. Journal of Central South University,2014,21(6):2372−2382. doi: 10.1007/s11771-014-2190-2
    [2]
    张振芳. 露天煤矿碳排放量核算及碳减排途径研究[D]. 徐州: 中国矿业大学, 2013.

    ZHANG Zhenfang. Study on carbon emissions accounting and carbon emission reduction approach of surface coal mine[D]. Xuzhou: China University of Mining and Technology, 2013.
    [3]
    胡明振,郭年琴. 矿用电动轮汽车运行效率及维修成本数学模型[J]. 煤炭学报,2009,34(11):1574−1578.

    HU Mingzhen,GUO Nianqin. The mathematical model of operation efficiency and maintenance cost of mine dump truck[J]. Journal of China and Society,2009,34(11):1574−1578.
    [4]
    王广慧,董新伟,邓 薇,等. 矿用变压器检修策略研究[J]. 中国矿业,2020,29(S2):383−389.

    WANG Guanghui,DONG Xinwei,DENG Wei,et al. Research on maintenance strategy of mining transformer[J]. China Mining Magazine,2020,29(S2):383−389.
    [5]
    张旭辉,张雨萌,王 岩,等. 融合数字孪生与混合现实技术的机电设备辅助维修方法[J]. 计算机集成制造系统,2021,27(8):2187−2195.

    ZHANG Xuhui,ZHANG Yumeng,WANG Yan,et al. Auxiliary maintenance method for electromechanical equipment integrating digital twin and mixed reality technology[J]. Computer Integrated Manufacturing Systems,2021,27(8):2187−2195.
    [6]
    徐 畅,王道元,李敬兆,等. 矿用设备智能安全监测与预知维护系统[J]. 工矿自动化,2021,47(3):79−82,88.

    XU Chang,WANG Daoyuan,LI Jingzhao,et al. Intelligent safety monitoring and predictive maintenance system for mining equipment[J]. Industry and Mine Automation,2021,47(3):79−82,88.
    [7]
    于嘉成,王 刚,刘卫东,等. 矿山设备全生命周期信息集成与工况判别算法研究[J]. 煤炭科学技术,2019,47(4):38−43.

    YU Jiacheng,WANG Gang,LIU Weidong,et al. Life-cycle information integration and working condition discriminational gorithm of mine equipment[J]. Coal Science and Technology,2019,47(4):38−43.
    [8]
    刘 威,郭直清,黄 敏,等. 基于MCMC算法的露天矿典型设备故障预测方法研究[J]. 煤炭科学技术,2019,47(10):51−57.

    LIU Wei,GUO Zhiqing,BAI Runcai,et al. Research on fault prediction method of typical equipment in open-pit mine based on MCMC Algorithm[J]. Coal Science and Technology,2019,47(10):51−57.
    [9]
    OZDEMIR B,KUMRAL M. Analysing human effect on the reliability of mining equipment[J]. International Journal of Heavy Vehicle Systems,2019,26(6):872−887. doi: 10.1504/IJHVS.2019.102716
    [10]
    OZDEMIR B,KUMRAL M. Appraising production targets through agent-based Petri net simulation of material handling systems in open pit mines[J]. Simulation Modelling Practice and Theory,2018,87:138−154. doi: 10.1016/j.simpat.2018.06.008
    [11]
    PERALTA S,SASMITO A P,KUMRAL M. Reliability effect on energy consumption and greenhouse gas emissions of mining hauling fleet towards sustainable mining[J]. Journal of Sustainable Mining,2016,15(3):85−94. doi: 10.1016/j.jsm.2016.08.002
    [12]
    刘 设. 基于随机过程的露天矿生产系统调度方法研究[D]. 沈阳: 沈阳工业大学, 2019.

    LIU She. Research on dispatching method of open-pit mine production system based on random process[D]. Shenyang: Shenyang University of Technology, 2019.
    [13]
    ANGELES E,KUMRAL M. Optimal Inspection and Preventive Maintenance Scheduling of Mining Equipment[J]. Journal of Failure Analysis and Prevention,2020,20(4):1408−1416. doi: 10.1007/s11668-020-00949-z
    [14]
    PATARAWAN C,HEIKKI S,HEIKKI K. Age-based maintenance for a fleet of haul trucks[J]. Journal of Quality in Maintenance Engineering,2018,24(4):511−528. doi: 10.1108/JQME-03-2017-0016
    [15]
    TOPAL E,RAMAZAN S. Mining truck scheduling with stochastic maintenance cost[J]. Journal of Coal Science and Engineering (China),2012,18(3):313−319. doi: 10.1007/s12404-012-0316-4
    [16]
    YU H, SOLVANG W D, SUN X. A decision-support model for operational planning of surface coal mining considering equipment failure[C]// International Symposium on Small-scale Intelligent Manufacturing Systems. IEEE: 2017: 89-94.
    [17]
    彭苑茹,刘勤明,吕文元,等. 基于故障状态演化的租赁设备定周期多维护策略研究[J]. 工业工程,2018,21(5):57−63.

    PENG Yuanru,LIU Qinming,LYU Wenyuan,et al. A research on periodic multi-maintenance strategy of leased equipment based on failure state evolution[J]. Industrial Engineering Journal,2018,21(5):57−63.
    [18]
    龙翔宇,刘葛辉,陈绍宽,等. 基于延迟时间的地铁车辆多级维修计划优化模型[J]. 铁道学报,2021,43(2):30−36.

    LONG Xiangyu,LIU Gehui,CHEN Shaokuan,et al. Optimum multi-level maintenance scheduling model for metro vehicles with delay time theory[J]. Journal of the China Railway Society,2021,43(2):30−36.
    [19]
    马 威. 基于健康指数的配电设备状态评估研究[D]. 西安: 西安理工大学, 2021.

    MA Wei. Research on state evaluation of power distribution equipment based on health index[D]. Xian: Xi’an University of Technology, 2021.
    [20]
    金 琳. 基于虚拟年龄的租赁设备多阶段预防性维护策略研究[D]. 上海: 上海交通大学, 2014.

    JIN Lin. Study on multi-period preventive maintenance policy for leased equipment based on virtual age method[D]. Shanghai: Shanghai Jiao Tong University, 2014.
    [21]
    周志恒,贺德强,陈彦君,等. 基于GA-BP神经网络的列车关键部件预防性维修优化模型及应用[J]. 铁道科学与工程学报,2021,18(6):1382−1391.

    ZHOU Zhiheng,HE Deqiang,CHEN Yanjun,et al. Optimization model and application of preventive maintenance of key components of train based on GA-BP neural network[J]. Journal of Railway Science and Engineering,2021,18(6):1382−1391.

Catalog

    Article views (94) PDF downloads (31) Cited by()
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return